Thomas Wood MAPM · Client-side Project Manager at Cockfosters Depot Upgrade

Making complex
projects move.

I manage end-to-end project delivery within a live depot environment, introducing new assets into a complex environment whilst ensuring the depot remains operational.

Design recovery · Commercial challenge · Stakeholder leadership

Professional portrait of Thomas Wood
Rail & infrastructure deliveryThomas Wood MAPM
RAIL & INFRASTRUCTURE DELIVERYProject portfolio CV available

01 / Delivery impact

Selected Project Achievements

Project outcomes and delivery.
Clear project context.

ROAD 26 · SATELLITE LOGISTICS DEPOT

£4mestimated reduction

Challenged a £9m contractor estimate and coordinated value engineering and re-tendering to develop a revised £5m scheme.

Estimated scheme costs; not a realised cash saving.

Explore the cost challenge

HV ROUTE · ENABLING WORKS

6 monthsfrom stalled design to site

Recovered a stalled concept design package through detailed design to site commencement, coordinating five design workstreams.

Approximate recovery period, not time saved against a baseline.

Explore the recovery

COCKFOSTERS · LIVE DEPOT DELIVERY

Live depotdelivery around active operations

Deliver works on an access-constrained site while the depot remains open and active. Plan and integrate all plant, machinery and people movements through the sole access route across live depot roads.

All work under ALO conditions, with critical activities planned into possessions and closures.

Explore delivery responsibilities

02 / Project evidence

Project Portfolio

The challenge, my contribution
and the outcome in view.

Materials handling alongside a supported excavation at the HV Route railway interface
HV ROUTE / CONSTRUCTION EVIDENCEView all 16 photographs

Design recovery · Construction readiness

HV Route
Enabling Works

My role Client-side Project Manager

A stalled concept design package needed a coordinated route through assurance, detailed design and the constraints of an operational railway.

My intervention
Challenged design capacity, increased design support and coordinated five workstreams, engineering assurance, early contractor input and closure-based delivery.
Outcome
Progressed from stalled concept design through detailed design to site commencement in approximately six months.

I owned delivery progression, resources and governance; engineers retained technical design responsibility.

  1. 01
    Unblock design

    Challenge capacity and strengthen design support.

  2. 02
    Coordinate readiness

    Bring assurance, contractor input and access together.

  3. 03
    Commence on site

    Progress the enabling package into construction.

Value engineering · Procurement

Road 26
Satellite Logistics Depot

My role Client-side Project Manager

The challenge
A contractor estimate of approximately £9m required a fresh challenge to scope, design assumptions and cost.
My intervention
Paused design, led the value engineering challenge, coordinated operational demand calculations and competitive re-tendering.
Outcome
A revised scheme estimated at £5m — approximately £4m below the £9m estimate. This is a forecast reduction in scheme cost.
See my commercial responsibilities
Existing track at Road 26Marked Road 26 site area and buffer-stop positionAnnotated layout showing the siding and material stockpile
View Road 26 photographs & layout
BUILD-OVER AGREEMENT ROAD 26
Challenge
requirements
Technical
evidence
Solution
accepted

An engineering-led route to stakeholder agreement.

Stakeholder influence · Technical coordination

Thames Water
Build-Over Agreement

My role Client-side Project Manager

The challenge
Proposed asset-protection requirements needed to be tested against the actual construction loading and site conditions.
My intervention
Challenged the requirements using surveys, loading assumptions and an engineering technical note, coordinating the technical and stakeholder inputs.
Outcome
Secured acceptance of a revised temporary asset-protection solution. The financial reduction has not been verified; the evidenced outcome is stakeholder agreement.
See my stakeholder responsibilities

03 / Accountability in practice

How I Deliver Projects

Challenge assumptions.
Influence decisions. Take accountability.

My role is to make delivery happen: direct the right specialists, challenge the plan and cost, secure decisions and intervene when progress or safety is at risk.

01

Programme & design recovery

I take ownership of the route back to delivery.

My accountability

I am accountable for design progression, programme, resources and governance. Planners maintain schedules and engineers own the technical design.

My intervention

I challenge critical-path logic, contractor variance and design capacity. I can authorise additional design support where it is affordable within the approved budget.

HV Route

Increased design support and coordinated five workstreams to progress a stalled package to site commencement in approximately six months.

Read the project evidence
02

Cost & commercial judgement

I challenge the cost before it becomes a commitment.

My accountability

I update forecasts with the Cost Manager, investigate overspend with QS support and assess contractor costs and payment applications.

My intervention

I challenge scope, assumptions and quotations; prepare change and spend requests; and recommend payment amounts for authorised certification.

Road 26

Paused design, challenged the proposed solution and coordinated value engineering and re-tendering: an estimated £9m scheme became an estimated £5m scheme.

Read the project evidence
03

Stakeholder influence

I turn a disputed requirement into an agreed way forward.

My accountability

I coordinate the stakeholder decisions and engineering inputs needed to resolve delivery constraints.

My intervention

I challenge requirements through evidence: surveys, loading assumptions and specialist technical assessment. Engineers retain responsibility for the technical solution.

Thames Water

Secured acceptance of a revised temporary asset-protection solution through an engineering technical note and stakeholder engagement.

Read the project evidence
04

Governance & risk

I make the delivery position clear enough to act on.

My accountability

I am accountable for consolidated Project Progress Reporting (PPR), bringing programme, cost, risk and discipline inputs into the four-week reporting cycle.

My intervention

I challenge inconsistent milestone forecasts, present at Pathway stage gates, coordinate engineering change submissions and escalate significant delay through NEC Early Warnings.

Management evidence

I complete Change Request Forms to capture changes and their cost, time and quality impacts, including budget and financial phasing. The form connects the change narrative to the project and financial assessments used in review.

View the supporting workflow
05

Safety & leadership

I intervene when safe delivery is at risk.

My accountability

I lead client-side safety assurance and incident investigations, supported by HSE and the Construction Manager.

My intervention

I exercise stop-work and restart authority after satisfactory corrective action. I use site inspections, safety stand-downs, coaching and lessons learned to address issues.

Management evidence

Inspection actions, corrective-action follow-up and investigation findings provide a record of intervention and learning.

View the supporting workflow
06

Procurement & mobilisation

I bring the team and the scope together for site.

My accountability

I author Works Information with discipline input, personally score bids using the prescribed evaluation and lead T-minus mobilisation.

My intervention

I align scope, programme, access and contractor readiness. Procurement owns the sourcing route and award; the Construction Manager owns the pre-construction checklist.

Project evidence

Road 26 competitive re-tendering and HV Route closure-based delivery show how I coordinate commercial and operational interfaces.

Read the project evidence
07

Mentoring & team development

I help colleagues take ownership.

My contribution

I voluntarily mentor an Assistant Project Manager to take responsibility for project activities, drawing on live delivery challenges.

My intervention

I co-present with colleagues to develop confidence and created practical project management onboarding guidance for a changing team.

Leadership in practice

Coaching, shared presentations and onboarding material help colleagues understand responsibilities and build their ability to lead work.

Leadership through delivery

Bring people together.
Keep responsibility clear.

I connect engineering, commercial, planning, construction, operations and external stakeholders around the decisions that unlock progress.

Challenging assumptions, coaching through safety interventions and following actions through to resolution are part of how I lead.

05 / Supporting detail

The controls behind delivery.

Explore the 12 workflows

For a closer look at my methods, the operating framework sets out the practical steps, decision points and responsibility boundaries across 12 management disciplines.

06 / Professional development

Qualifications
& competencies

Qualifications carried forward from V2. Replacement certificates, exact titles and current validity remain to be verified.

Professional qualifications

  • APM Project Professional Qualification PPQ
  • PRINCE2 Foundation
  • BA (Hons) Business Management

Safety & rail records

  • Mental Health First Aid
  • Basic Track Awareness BTA
  • Passport to Depot
  • Sentinel sponsorship Sponsorship, not a qualification

Start a conversation

A project to move forward?
Let's talk.

For rail and infrastructure project management opportunities.