← Back to the portfolio

Supporting project management framework

The detail
behind the decisions.

Twelve practical workflows, drawn from my documented responsibilities. Each distinguishes what I own, what I challenge and where specialist authority sits.

Start with my accountability and interventions

Explore the operating framework

12 management disciplines

Select a discipline for its workflow and project evidence. These controls support the responsibilities shown on the main portfolio.

Change control in practice

Capture the change and its project impacts.

I complete Change Request Forms (CRFs) to document a change and its cost, time and quality impacts, including the budget and financial phasing. The form brings these assessments together with supporting documents for review and subsequent change control.

01 · Programme / P6

Client and contractor schedules are maintained concurrently, with the same performance metrics.

  1. Direct planners to maintain the client-side P6 programme and review contractor programmes for each instructed tranche.
  2. Review planned vs actual, milestones, critical path and four-week look-back / look-ahead.
  3. Challenge contractors to explain variance and provide mitigation commentary.
  4. Minute review meetings, track local actions and use NEC Early Warnings / risk reduction meetings for significant delay.

Responsibility: PM directs and challenges; planners maintain schedules.

Project evidence: HV Route: progressed from stalled concept design through detailed design to site commencement in approximately six months (a recovery period, not time saved).

View project evidence
02 · Cost & Forecasting

I complete the budget and financial phasing sections of CRFs to show how a project change affects cost and when expenditure is expected.

  1. PM + Cost Manager

    Review the forecast

    Review EFC, spend, accruals and programme alignment; investigate variances with QS support.

  2. PM + specialists

    Capture the change impacts

    Complete the CRF description and justification, connecting the change in cost to its time, quality, risk and resource implications.

  3. PM + Cost Manager

    Complete the budget impact

    Record the affected control accounts, existing budget, previous changes, this change, cumulative impact and remaining budget. Identify pending changes separately.

  4. PM + Cost Manager

    Complete financial phasing

    Set out when the change affects spending across financial years and reporting periods. Reconcile the phased change to the cost summary.

What financial effect does the change have?

Cost increase or reduction

Quantify the change against the baseline and explain the estimate, scope and funding assumptions.

Budget transfer

Record the affected control accounts and the movement of budget between them.

Change in spending profile

Capture when expenditure moves between reporting periods, including changes with no overall increase in cost.

Working documents

The CRF, Finance Budget Summary and Periodic Phasing sheets bring the change narrative, budget impact and timing of expenditure together.

Responsibility: PM completes and coordinates the change assessment with Cost Manager and specialist inputs. The Cost Manager implements approved baseline changes.

Project example: Road 26: challenged a £9m estimate, leading to a revised estimated £5m solution.

View the project account
03 · Commercial / NEC

Verify expenditure and administer contractual processes without overstating approval authority.

  1. Review labour, plant, material records and site reporting under cost-reimbursable ECI.
  2. Assess quotations and contractor payment applications; recommend amounts for certification.
  3. Prepare and present authority-to-spend requests; Commercial Manager raises POs.
  4. Manage Early Warnings and PM Instructions; independently assessed one Compensation Event.

Responsibility: PM assesses and recommends; authorised signatory signs CPAF.

Project evidence: Contractor cost scrutiny and tender challenge.

04 · Health & Safety

Client-side safety assurance and intervention.

  1. Prepare internal CDM assessments and coordinate acceptance of contractor SSOW, TBS and ITPs.
  2. Conduct PGIs using SafetyCulture / IE2 and track outstanding actions.
  3. Exercise stop-work and restart authority after satisfactory corrective action.
  4. Lead incident investigations with HSE and Construction Manager support.

Responsibility: PM leads client-side assurance; technical specialists retain their own statutory duties.

Project evidence: Safety stand-downs, coaching and lessons learned.

05 · Governance & Change Control

I complete CRFs to capture project changes and their cost, time and quality impacts, including the associated budget and financial phasing.

  1. PM

    Describe the change

    Record what is changing, why it is needed, the affected scope and the consequences of not proceeding.

  2. PM + discipline inputs

    Assess cost, time and quality

    Complete the impact assessment with the relevant specialists, recording the effects on delivery and any related risks or resource needs.

  3. PM + Cost Manager

    Set out budget and phasing

    Complete the financial impact and periodic spending profile so the change is reflected in both the budget assessment and the timing of expenditure.

  4. PM + reviewers

    Submit and track

    Bring the form and supporting documents together for review, resolve comments and follow the change through the applicable approval and implementation process.

The project impacts recorded in the form

Cost

Financial effect, affected control accounts, funding route and any budget transfer or efficiency.

Time

Programme consequences, affected milestones and before/after schedules where the programme changes.

Quality

Quality impacts and causes, including planning, design, survey or asset-information gaps, and construction issues.

Evidence of how I manage change

The CRF is a practical example of the forms I complete to capture and assess project change. Its impact assessment, budget summary, phasing and supporting-document register show how the change is documented for review.

I coordinate wider design and engineering review where required and link the relevant assessments and affected documents.

Alongside change control, I consolidate four-week PPR reporting, coordinate Pathway stage gates and engineering change submissions, and maintain the project management plan.

Responsibility: PM completes and coordinates the change submission with discipline specialists. Programme Services controls CRF status updates; the relevant authorities review and approve changes. Approved changes are then implemented by the responsible teams.

06 · Engineering

Coordinate technical inputs and project decisions without claiming engineering design authority.

  1. Engineer leads design assurance and technical acceptance documents.
  2. PM facilitates optioneering, value engineering and stakeholder decisions.
  3. Coordinate DCF forums and ITP acceptance; Engineer / Designer approve technical changes.
  4. Review materials against TfL Approved Product Register and manage interface phasing.

Responsibility: Engineers own technical design; PM owns delivery impacts and applicable PM sign-off.

Project evidence: Thames Water: technical note accepted for revised build-over solution.

View project evidence
07 · Benefits & Value

Quantify expected benefits and defend investment cases.

  1. Coordinate TRS and business case development.
  2. Contribute operational capacity and logistics calculations.
  3. Prepare Project Manager's Assessment of anticipated savings.
  4. Present spend-to-save justification; distinguish forecast from realised benefits.

Responsibility: PM develops investment justification; benefits realisation ownership remains to be confirmed.

Project evidence: Road 26: reducing reliance on unreliable EV logistics.

View project evidence
08 · Logistics & Access

Plan strategic railway logistics and access constraints.

  1. Calculate Road 26 peak throughput using train pathing assumptions agreed with Fleet / Ops.
  2. Put forward closure and possession needs with Construction Manager; access team formalises them.
  3. Coordinate electrical switch-out requests and eight-week advance substation permits.
  4. Organise multi-contractor interface meetings; CM leads daily site logistics.

Responsibility: PM coordinates strategic interfaces; specialist teams own formal access and site controls.

Project evidence: HV Route construction during operational closures.

View project evidence
09 · Procurement & Mobilisation

From Scope preparation through structured tender review and contractor readiness.

  1. Procurement selects the route; PM authors Works Information with discipline workshops.
  2. Coordinate and personally score bids using the prescribed evaluation template.
  3. Procurement presents the formal award recommendation.
  4. PM leads T-minus mobilisation; CM owns separate pre-construction checklist.

Responsibility: Procurement owns sourcing route and award; PM owns mobilisation.

Project evidence: Road 26 competitive re-tendering and procurement challenge.

View project evidence
10 · Risk / ARM

Where a risk leads to a project change or drawdown, I use the CRF to capture the impacts, funding requirement and financial phasing alongside the risk assessment.

  1. PM + Risk Manager

    Review the risk

    Assess likelihood, impact and EMV in ARM; assign mitigation actions and review the exposure.

  2. PM + specialists

    Capture the change in the CRF

    Describe the event, its cost, time and quality impacts, the funding need and the consequences of not proceeding.

Was the cost increase already identified as a risk?

Yes

Link the risk identifier, ARM entry date and pre-drawdown EMV to the justification.

No / record incomplete

Explain the circumstances and establish the supporting assessment and funding route before a decision. Document the gap and supporting rationale.

  1. PM + Cost Manager

    Complete budget and phasing

    Record the proposed funding change, its periodic spending profile and any residual exposure. Link the supporting assessments.

  2. PM + reviewers

    Submit the change

    Bring the completed CRF and supporting documents into the applicable review and approval process.

  3. Cost Manager + risk owners

    Implement and monitor

    Implement approved funding changes and review the resulting risk position and mitigation actions with the Risk Manager.

Does residual risk remain?

Yes

Retain the residual exposure, owner and mitigation actions; continue review.

No

Record the assessment supporting closure and update the risk position.

Related control

Use NEC Early Warnings and risk-reduction discussions where applicable. These contractual communications remain distinct from internal funding approval.

Responsibility: PM develops and monitors the risk position with the Risk Manager and completes the change submission with relevant specialist inputs. The Cost Manager implements approved funding adjustments.

11 · Design Delivery

Control design progression from concept to C-status issue.

  1. Engineer owns technical baseline, V&V matrix and detailed assurance.
  2. PM accountable for design programme, resources and governance.
  3. Challenge CTR and authorise affordable additional design support.
  4. Sign acceptance certificates, chase signatures and issue C-status designs for pricing.

Responsibility: Engineer responsible for technical design; PM accountable for delivery.

Project evidence: HV Route: five workstreams coordinated into one enabling package.

View project evidence
12 · Resourcing

Resource demand, cost and timesheet controls.

  1. Review staff hours against activities and WBS codes before approval.
  2. Review Engineer-developed Cost-Time-Resource forecasts.
  3. Challenge resource shortfalls and adjust support within budget authority.
  4. Enter and maintain own resource demand in Smartcore using proxy rights.

Responsibility: PM approves relevant timesheets and enters own Smartcore demand.

Project evidence: Design support increased during HV Route recovery.

View project evidence

Accountability stays with the right person.

I am accountable for project delivery and applicable PM sign-off. Engineers own technical design and assurance; planners maintain schedules; Procurement owns the sourcing route and award; authorised signatories approve formal payment certification.

The framework records one independently completed Compensation Event assessment. Smartcore access covers my own project resource demand, not approval of other Project Managers’ allocations. Benefits-realisation ownership remains to be confirmed.

Discuss a project or opportunity